Wi Neera Walkway Sea Wall Repair

Sea wall renewal along Wi Neera street. From jetty to coast guard building. Year one details report into condition and recommendations.

Project Update

August 2024 - Northern End - Sea Wall repairs were completed in November; arborist work has been completed to remove several low hanging branches and Watercare have completed the replacement of the old watermain feeding across to Papahua.  Construction onsite has seen all the concrete footpath poured with the path now open with temporary balustrades in place.  Half the final balustrades are now in place, the balance is due to be installed in the next 10 days.  The project will finish onsite in early September.

 

At a glance
Status
Active
Categories
Parks and reserves
Maaori wards
Tai Runga Takiwaa
General wards
Whāingaroa
Towns
Raglan
Completion date
September 2024