Raglan Wastewater Treatment Plant Upgrades
Raglan Wastewater Treatment Plant Upgrades
Project Update
February 2025 - The project is on track and progressing well. The reactor structure is complete with internal benching being planned. The inlet works platform is built up, and the screening equipment installation is scheduled for during November. The building is complete, electrical works have commenced and the mechanical pipework fabrication is also underway.
At a glance
Status
Active
Categories
Waters
Maaori wards
Tai Runga Takiwaa
General wards
Whāingaroa
Towns
Raglan
Completion date
N/A