Harrisville Road bridge replacements
Flood prevention and resilience project. Harrisville Road bridge is being redesigned to increase the amount of water that can pass underneath. This project will also see a number of key services (water, power etc) lift with the bridge as well as an upgraded intersection with Ryders Road, Dominion Road & George Street.
Project updates
December 2024 – Currently being Designed and Consented which will be complete by mid-2025. Construction will be dependent on co-funding from NZTA/Waka Kotahi
At a glance
Status
Active
Categories
Roading
Maaori wards
Tai Raro Takiwaa
General wards
Tuakau-PÅkeno
Towns
Tuakau
Completion date
July 2026